Question: NETWORK: PERT 1 Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES ( days ) to tml tp te A - - - 2 3
NETWORK: PERT
Consider the following table:
ACTIVITY PREC. ACT. TIME ESTIMATES days
to tml tp te
A
B
C
D A
E B
F C
G D E F
Construct a PERT network.
NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before
proceeding to the next sections.
By using ES EF LF LS find the slack of each activity and the critical path.
Find the completion time and the standard deviation sigma for the project round off the standard
deviation to the nearest hundredth: two decimal places.
What is the completion time at confidence level?
What is the likelihood of this project being completed in more than days?
Between and days?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
