Question: NETWORK: PERT 1 Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES ( days ) to tml tp te A - - - 2 3

NETWORK: PERT 1
Consider the following table:
ACTIVITY PREC. ACT. TIME ESTIMATES (days)
to tml tp te
A ---234
B ---357
C ---246
D A 345
E B 2513
F C 246
G D, E, F 456
1) Construct a PERT network.
[NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before
proceeding to the next sections.]
2) By using ES, EF, LF, LS, find the slack of each activity and the critical path.
3) Find the completion time and the standard deviation (\sigma ) for the project round off the standard
deviation to the nearest hundredth: two decimal places.
4) What is the completion time at 99% confidence level?
5) What is the likelihood of this project being completed in more than 14 days?
6) Between 11 and 13 days?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!