Question: NETWORK: PERT 4 WEEK 6 Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES (days) t o t ml t p t e A ---
NETWORK: PERT 4 WEEK 6
Consider the following table:
ACTIVITY PREC. ACT. TIME ESTIMATES (days)
to tml tp te
A --- 1 2 3
B A 2 4 6
C B 1 4 7
D B 3 4 5
E C 1 3 5
F D, E 2 3 4
1) Construct a PERT network.
[NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]
2) By using ES, EF, LF, LS, find the slack of each activity and the critical path.
3) Find the completion time ( ) and the standard deviation () for the project round off the standard deviation to the nearest hundredth: two decimal places.
4) What is the completion time at 95% confidence level?
5) What is the likelihood of this project being completed earlier than 14 days?
6) Between 13 and 15 days?