Question: Network Scheduling Consider the following network scheduling problem. Identify and list all the paths in the network leading from Start to Finish and their duration.
Network Scheduling
Consider the following network scheduling problem.

Identify and list all the paths in the network leading from Start to Finish and their duration. Which path is critical? Why? Indicate the critical path on the network with a different color. Which activity will you crash to reduce the project duration by three days? Explain.
*Also Need help with free and total slack*