Question: Networking The following table indicates the duration estimates in work days. Job Predecessors Most Likely A -- 20 B -- 3 C B 8 D
Networking
The following table indicates the duration estimates in work days.
| Job | Predecessors | Most Likely |
| A | -- | 20 |
| B | -- | 3 |
| C | B | 8 |
| D | A | 5 |
| E | A | 8 |
| F | E,C | 7 |
| G | D,F | 7 |
- Draw the CPM network, showing the Earliest Start, Earliest Finish, Latest Start and Latest Finish Times.
- Write the critical path and the most likely duration of the project.
- The sponsor asks for a change that will mean activity C will take an extra 8 days. Is there sufficient slack on activity C to allow this change? As project manager what steps should you take to respond to this request?
- Define the project baseline plan and describe its three components. Discuss the importance of the project baseline plan and describe how the baseline is used to manage the project execution.
- After an organization has developed a list of potential suppliers, how should the organization evaluate each supplier individually? Discuss.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts