Larry Edison is the director of the Computer Center for Buckly College. He now needs to schedule the staffing of the center. It is open from AM until midnight. Larry has monitored the usage of the center at various times of the day and determined that the following number of computer consultants qualified graduate students are required.
tableTimeMinimumRequiredNoon to Noon PM PM to PMPM to Midnight,
Click here for the Excel Data File
Two types of computer consultants can be hired: fulltime and parttime. The fulltime consultants work for eight consecutive hours in any of the following shifts: morning AM to PM afternoon noon to PM and evening PM to midnight Fulltime consultants are paid $ per hour. Parttime consultants can be hired to work any of the four shifts listed in the table. Parttime consultants are paid $ per hour. An additional requirement is that during every time period, there must be at least two fulltime consultants on duty for every parttime consultant on duty.
Formulate a spreadsheet model for this problem. Then use Solver to solve the model.
a Larry would like to determine how many fulltime and parttime consultants should work each shift to meet the above requirements at the minimum possible cost.
Note: Enter O if no workers are assigned during that particular shift.
tableFull Time,,Part TimeE AM to PMNoon to PMtable PM toMidnight AM to Noon,Noon to PM PM to PMtable PM toMidnight
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock