Question: NEW YORK When a shorter construction schedule was implemented for the Henry J . Carter Specialty Hospital and Nursing Facility in Harlem, it forced designers
NEW YORK When a shorter construction schedule was implemented for the Henry J Carter Specialty Hospital and
Nursing Facility in Harlem, it forced designers and contractors to reevaluate their plans to overcome any potential delays.
The original objective was to relocate ColerGoldwater Specialty Hospital and Nursing Facility later renamed to Henry J
Carter Specialty Hospital and Nursing Facility from Manhattans Roosevelt Island to the Harlem neighborhood of New York City. The $ million project would be divided into two projects: renovating square feet of the former North General Hospital in Harlem and building square feet of space next door to accommodate a new, bed nursing facility.
Had the original timeline been maintained, the hospital and separate nursing facility would still be under construction with a completion date set for March These plans were overhauled, however, when New York Citys mayor made a special announcement.
We started schematic design and realized quickly that Mayor Bloomberg had announced that Cornell University and its partner, the TechionIsrael Institute of Technology, were going to be awarded an applied sciences technology school, said Marsha Whitt, principal at Array Architects, based in King of Prussia, Pa and project manager for the Henry J Carter facility.
The technology school was set to build on the same Roosevelt Island site where the ColerGoldwater hospital was located. The only problem was that the hospital needed to be demolished quickly. The expedited demolition date moved the completion and patientmove date for Henry J Carter up to November and shrank the schedule by months.
Thats when we had to back up and relook at the project and look at how we were going to approach it How long was design going take? How long was construction going to take? How were the design team and the construction managers going to work together to meet these accelerated deadlines? Whitt said.
A new time frame wiped out the designdevelopment process. The solution was to regroup and implement integrated project delivery IPD strategies and a collocation system. Array went straight from schematic design to construction documents.
This forced the projects construction manager, Gilbane McKissack a joint venture between Providence, RI.based Gilbane and Nashville, Tenn.based McKissack & McKissack to start looking at how they could quickly get resources onsite.
All stakeholders involved in the development process came together in fullteam meetings. The strategy united the design team, construction manager and hospital owner in one location, and the collaboration accelerated the decisionmaking.
Additionally, performance incentives that included shared cost and schedule metrics for both the contractor and design team helped to maintain the team effort.
Youre joined at the hip by money, but since we were collocated, we put that piece aside and started to work as a cohesive team we were all working toward the same goal, Whitt said.
One critical component of adjusting to the tighter schedule involved dividing the two projects into multiple bid packages, which helped speed up information delivery, contract award and start of construction.
Traditionally you may have a site package, an exterior package and a fitout package. On this, we ended up with packages because we broke it out by what could be purchased and when to get it onsite and get it installed, Whitt said.
The client, contractor and design team worked sidebyside to review and approve packages. That process helped with getting parts of construction completed earlier things such as elevators, major medical equipment and the mechanical, electrical and plumbing
Just when the process was starting to go smoothly, the development process for the hospital and new nursing facility hit a new obstacle Hurricane Sandy. Luckily, the Harlem site was not flooded, but it prompted a review of storm and flood elevations for the facilities. The project team included additional equipment protection and elevated electrical equipment on higher pads.
The Henry J Carter Specialty Hospital and Nursing Facility opened on time, and Array is now involved in Day revisions, assessing what else is needed or needs to be adjusted after occupant movein
QUESTION
A project schedule indicates what needs to be done, which resources must be utilised, and when the project is due. It's a timetable that outlines start and end dates and milestones that must be met for the project to be completed on time.
Examine the additional ways to measure schedule performance. Apply the theory to the case study project appropriately and adequately.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
