The table below shows the complete project plan and includes all the activities with its immediate...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
The table below shows the complete project plan and includes all the activities with its immediate predecessor activity and time taken by each activity. ANSWER THE FOLLOWING QUESTION Activity Duration (weeks) A B C D E F G H 1 J K L M N Immediate predecessor A B C C E D E, G C F.I J J H K, L 2 4 10 6 4 5 7 9 7 8 4 5 2 6 What is the earliest start (ES) of activity B ? What is the latest start (LS) of activity M ? What is the latest finish (LF) of activity H? What is the slack (SL) value of activity D ? What is the earliest finish (EF) of activity K? What is the earliest start (ES) of activity G? What is the slack (SL) value of activity A? What is the earliest finish (EF) of activity M? What is the slack (SL) value of activity K ? What is the latest start (LS) of activity F? What is the critical path for this project? What is the latest start (LS) of activity 1 ? What is the earliest finish (EF) of activity I? What is the latest finish (LF) of activity G? What is the latest start (LS) of activity K ? What is the latest finish (LF) of activity B? What is the earliest start (ES) of activity H? What is the slack (SL) value of activity H? Choose... 1 40 34 2 29 37 23 22 ABCEFJLM 33 20 4 18 ABCEFJLN A 6 0 42 Choose... Choose... Choose... Choose... Choose... O The table below shows the complete project plan and includes all the activities with its immediate predecessor activity and time taken by each activity. ANSWER THE FOLLOWING QUESTION Activity Duration (weeks) A B C D E F G H 1 J K L M N Immediate predecessor A B C C E D E, G C F.I J J H K, L 2 4 10 6 4 5 7 9 7 8 4 5 2 6 What is the earliest start (ES) of activity B ? What is the latest start (LS) of activity M ? What is the latest finish (LF) of activity H? What is the slack (SL) value of activity D ? What is the earliest finish (EF) of activity K? What is the earliest start (ES) of activity G? What is the slack (SL) value of activity A? What is the earliest finish (EF) of activity M? What is the slack (SL) value of activity K ? What is the latest start (LS) of activity F? What is the critical path for this project? What is the latest start (LS) of activity 1 ? What is the earliest finish (EF) of activity I? What is the latest finish (LF) of activity G? What is the latest start (LS) of activity K ? What is the latest finish (LF) of activity B? What is the earliest start (ES) of activity H? What is the slack (SL) value of activity H? Choose... 1 40 34 2 29 37 23 22 ABCEFJLM 33 20 4 18 ABCEFJLN A 6 0 42 Choose... Choose... Choose... Choose... Choose... O
Expert Answer:
Answer rating: 100% (QA)
What is the earliest start ES of activity B Answer The earliest start of activity B is 10 weeks This is because activity B has an immediate predecessor of activity A and the duration of activity A is ... View the full answer
Related Book For
An Introduction to Statistical Methods and Data Analysis
ISBN: 978-1305269477
7th edition
Authors: R. Lyman Ott, Micheal T. Longnecker
Posted Date:
Students also viewed these general management questions
-
An investor based in the United States wishes to invest in Swiss bonds with a maturity oi one year. Suppose that the ratio of the price levels of a typical consumption basket in the United States...
-
A financial analyst based in the United States has computed both accounting and NPV breakeven sales levels for a project under consideration using straight-line depreciation over a 6-year period. The...
-
Sales from weight-reducing agents marketed in the United States represent sizable amounts of income for many of the companies that manufacture these products. Psychological as well as physical...
-
a. Suppose that hedonic wage studies indicate a willingness to pay $50 per person for a reduction in the risk of a premature death from an environmental hazard of 1/100,000. If the exposed population...
-
Researchers seem to have a lot of fun testing different nudges to see how well they work. In one experiment, they placed mirrors in shopping carts so customers at a grocery store were forced to look...
-
Explain the nature of the Third World debt crisis that emerged in the 1970s and 1980s.
-
Explain ethnocentrism, cultural relativism, and the ways anthropology has evolved under changing working conditions.
-
Nakashima Gallery had the following petty cash transactions in February of the current year. Feb. 2 Wrote a $ 400 check, cashed it, and gave the proceeds and the petty cashbox to Chloe Addison, the...
-
Does an excellent Employee Value Proposition make their employees want to stay with a company for a long time? how
-
Greg Gordon manages the 10,000-square-foot multilevel laser tag arena at LazerLite. This arena combines cutting-edge computer technology with action-oriented team play; in a futuristic environment...
-
On January 1, 2011, ABC Company acquired a building for P5,000,000. The building is depreciated using straight line method based on a useful life of 10 years with no residual value. On January 1,...
-
Determine the amount of taxable income that should be reported by a cash-basis taxpayer in 2023 in each of the following independent cases: Required: a. A taxpayer completes $750 of accounting...
-
White Diamond Flour Company manufactures flour by a series of three processes, beginning with wheat grain being introduced in the Milling Department. From the Milling Department, the materials pass...
-
Last year Minden Company introduced a new product and sold 2 5 , 8 0 0 units of it at a price of $ 9 3 per unit. The product's variable expenses are $ 6 3 per unit and its fixed expenses are $ 8 3 1...
-
NYI Corporation manufactures decorative window glass in two sequential departments. These data pertain to the month of August: Department 1 Direct Materials used for production Department 2 $ 5 5 , 0...
-
Express in terms of 1. -343 - 343 = (Simplify your answer. Type your answer in the form a + bi.)
-
You have two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 -161,000 -111,000 1 29,800 59,700 2 50,100 45,100 3 70,100 29,700 4 90,000 19,900 Irrespective of the project, the...
-
Determine the reactions in supports A and D and connections B and C. Sketch its shear and moment diagram and determine the magnitude ankoration of the maximum shear and moment for every member. 18 3...
-
Use the binomial distribution with n = 20 and = .5 to compare the accuracy of the normal approximation to the binomial. a. Compute the exact probabilities and corresponding normal approximations for...
-
Refer to Exercise 4.11. a. Are the events A and B independent? Why or why not? b. Are the events A and C independent? Why or why not? c. Are the events B and C independent? Why or why not?
-
An experimenter is interested in examining the bond strength of a new adhesive product prepared under three different temperature settings (280 F, 300 F, and 320 F) and four different pressure...
-
Evaluate Mephisto Products current approach to sales. Why has it been relatively successful to date?
-
What problems can you anticipate if Tony Bullins goes ahead and changes the sales team and selling philosophy?
-
How does the role of selling tend to differ between: (a) industrial products (B2B)? (b) consumer products (B2C)?
Study smarter with the SolutionInn App