Question: Nicholas and Steyn define life cycle costs to include all costs of a system throughout its full cradle - to - grave life cycle. Which

Nicholas and Steyn define life cycle costs to include all costs of a system throughout its full cradle-to-grave life cycle. Which of the following responses correctly states a valid purpose of life cycle cost analysis?
Group of answer choices
to establish target costs for operating, maintaining, and disposing of the end-item system
to develop a time phased budget for the project
to control the cost of systems development
to establish a rough order of magnitude estimate for the project proposal