Question: Nicolas is a project manager managing a six-month project for his organization. During a status meeting, the director of development notes that he would like
Nicolas is a project manager managing a six-month project for his organization. During a status meeting, the director of development notes that he would like to see two additional features added to the project's deliverable. Nicolas hesitates and points out that the additional features are not in scope for the project. The director waves him off and states that he could cover the costs if needed. Which of the following processes addresses this situation? This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. option A Control Quality option B Control Scope option C Validate Scope option D Plan Scope Management