Question: No. 3 Please solve this problem using LUC (Least Unit Cost) Method b. What are the planned order releases for part B using POQ =

No. 3 Please solve this problem using LUC (Least Unit Cost) Method
b. What are the planned order releases for part B using POQ = 2 for both parts A and B? 3. A company has estimated net requirements for a particular part as follows: Month 2 3 4 5 6 7 8 9 10 11 12 1 Requirements 100 10 15 20 70 250 250 250 250 40 0 100 Ordering cost associated with this part is $300. Estimated inventory carrying cost is $2 per unit per month calculated on average inventory. Currently no parts are available in inventory. The company wishes to know when and how much to order over the next 12 monthsStep by Step Solution