2a). VAC (Variance at Completion)

You are managing a project that is expected to take 11 months, and the expenses are budgeted to be $1500 per month. 5 months after the project started, you find out that the project is 30% complete and that you have spent $13000.

What is the VAC (Variance at Completion) of the project at this point?

2b). TCPI (To Complete Performance Index)

You are managing a project that is expected to take 10 months, and the expenses are budgeted to be $11500 per month. 2 months after the project started, you find out that the project is 20% complete and that you have spent $11000.

What is the TCPI (To Complete Performance Index) of the project at this point?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Economics Questions!