Question: No longer need an answer to this. Please answer my other pending questions. Thank you :) Consider the deli process that we discussed in class
No longer need an answer to this. Please answer my other pending questions. Thank you :)
Consider the deli process that we discussed in class consisting of 3 stations: Take orders, Pick orders and Pack orders. What is the current max throughput rate of the process if the processing times for taking, picking and packing are 2 minutes, 5 minutes and 3 minutes, respectively? Assume that each station has a designated worker.
10/hour
20/hour
12/hour
30/hour
6/hour
Considering the deli process described before, which of the following changes will result in the highest throughput rate
Group of answer choices
Shifting 2 minutes of work from Pick orders to Take orders
Adding 1 more worker to Take orders
Adding 1 more worker to Pick orders
Adding 1 more worker to Pack orders
Shifting 1 minute of work from Pick orders to Take orders