Question: No. WBS Name Duration Predecessors IT PROJECT 1.1 Definition 1.1.1 Interviews 2d 1.1.2 Prep Req Doc 2d 1.1.3 Prep Proj Plan 2d GOODNOVIAWN- 1.1.4 Prep

No. WBS Name Duration Predecessors IT PROJECT 1.1 Definition 1.1.1 Interviews 2d 1.1.2 Prep Req Doc 2d 1.1.3 Prep Proj Plan 2d GOODNOVIAWN- 1.1.4 Prep Proposal 2d 1.2 Analysis 1.2.1 Interviews 1.2.1.1 Management 1d 1.2.1.2 Supervisor 2d 11 1.2.1.3 Technical 2d 12 1.2.1.4 Clerical 2d 13 1.2.2 Anal Existing Doc 3d 14 1.2.3 Synthesis 3d 15 1.2.4 Functional Spec 5d 16 1.2.5 Re-estimate Plan 1d 15 17 1.2.6 Development Prop 4d 16 18 1.2.7 Presentation 1d 17 19 1.3 Design 20 1.3.1 System Design 5d 18 21 1.3.2 Walk-through 1d 20 22 1.3.3 File Design 2d 21 23 1.3.4 Walk-through 1d 22 24 1.3.5 Acc Test Plan 4d 23 25 1.3.6 Design Spec 5d 23 26 1.4 Construction 27 1.4.1 Plan the Integration 4d 25 28 1.4.2 Module Design 5d 29 1.4.3 Walk-through 1d 30 1.4.4 Plan Module Testing 2d 1.4.5 Coding 5d WNWWNNN 3 1.4.6 Module Test 5d NUO 33 1.4.7 User Documentation 5d 4 1.5 System Test 5d
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts