Question: Normal Crash Normal Crash duration duration cost cost Activity Precedent (days) (days) (PHP) (PHP) A 120 100 12000 14000 B 20 15 1800 2800 C

Normal Crash Normal Crash duration duration cost cost Activity Precedent (days) (days) (PHP) (PHP) A 120 100 12000 14000 B 20 15 1800 2800 C B 40 30 16000 22000 D 30 20 1400 2000 E D 50 40 3600 4800 B 60 45 13500 18000 What is the critical path of the project? O A) B-A-F-E O B) B-C-D-E O C) B-F-D-E O D) A-B-F-D-E O E) A-B-C-D-E