Question: Normal Crashed Activity Duration ( day ) Total Cost ( in $US ) Duration ( day ) Total Cost ( in $US ) A 4

Normal Crashed
Activity Duration (day) Total Cost (in $US) Duration (day) Total Cost (in $US)
A 4 $1,2002 $2,500
B 4 $1,5003 $1,900
C 5 $1,9003 $3,000
D 9 $2,3008 $2,800
E 7 $1,7006 $3,000
F 5 $2,8003 $6,100
G 3 $1,7002 $2,500
Your boss asks if you can shorten the project by one more day. She tells you the indirect project costs are $800.00/day. What do you tell her? Can you do it? What activity do you shorten, and what is the additional cost?