Question: Normal Time Crash Time Crash Cost Activity (Days) (Days) per day (5) A 6 6 B 10 8 Stam C 5 4 D 4 1
Normal Time Crash Time Crash Cost Activity (Days) (Days) per day (5) A 6 6 B 10 8 Stam C 5 4 D 4 1 $100 $300 $700 $500 $650 E 9 7 1 F 2 A network of a small project with six activities is shown above, also shown are the normal time and crash time, and the crash cost per day of each activity Refer to the above network and table. If we have to optimally crash the project i) by 1 day we should crash activity it by 2 days we should crash activity/activities im) by 3 days we should crash activity/activities
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
