Question: Norton industries is installing a new computer system. The activities, the immediate predecessor of each activity, and the activity times of the project are given
Norton industries is installing a new computer system. The activities, the immediate predecessor of each activity, and the activity times of the project are given in the following table.
| Activity | immediate predecessor | time(weeks) |
| A | ------ | 3 |
| B | ----- | 6 |
| C | A | 2 |
| D | B,C | 5 |
| E | D | 4 |
| F | E | 3 |
| G | B,C | 9 |
| H | F,G | 3 |
a) Draw an AON diagram of the project, including activity times.
b) Determine ES, EF, LS, LF, and slack for each activity. Summarize calculations in the form of a table giving the activity schedule.
c) What are the critical activities and what is the project completion time?