Question: Not sure if my answer is correct. Can someone please confirm? A construction company entered into a fixed-price contract to build an office building for
A construction company entered into a fixed-price contract to build an office building for $20 million, Construction costs incurred during the first year were $6 million, and estimated costs to complete at the end of the year were $9 million. The company recognizes revenue over time according to percentage of completion. During the first year the company billed its customer $7 million, of which $5 milion was collected before year-end. What would appear in the year-end batance sheet related to this contract? Note: Enter your answers in whole dollars and not in millions (i.e., $4 million should be entered as $4,000,000 )
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts