Question: Note that # 1 8 shows that activity C can't be crashed at all by showing the crash time and cost to be the same
Note that # shows that activity C can't be crashed at all by showing the crash time and cost to be the same as the normal time and cost.
However, # shows that activity E can't be crashed at all by showing the crash time and cost to be