Question: ( Note: This question only tests your understanding of the relationship between duration, units and work in a scheduling context. It does not require you

(Note: This question only tests your understanding of the relationship between duration, units and work in a scheduling context. It does not require you to actually use MS Project.)
You are responsible for managing a project's schedule in MS Project. Among other tasks, the schedule contains a gardening task, which is defined as follows:
The tasks duration is 4 days.
The task is defined as an auto-scheduled, effort driven, fixed duration task.
The following resources have been allocated to the task:
Resource Name Units Resource Type
gardener 400% Work
Looking at the project options in MS Project, you find that one day equals 7.5 hours.
How many man-hours in total are associated with this gardening activity according to MS Project? (If necessary, round to two decimal places.)
man-hours
It is now decided that 3 additional gardeners should be added to the gardening task.
So, you increase the number of gardeners by 300% in the Task Information dialog for the for the gardening task.
What is the new task duration in MS Project? (If necessary, round to two decimal places.)
days
What is the new total of man-hours associated with this task in MS Project? (If necessary, round to one decimal place.)
man-hours

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!