Question: ( Note: This question only tests your understanding of the relationship between duration, units and work in a scheduling context. It does not require you
Note: This question only tests your understanding of the relationship between duration, units and work in a scheduling context. It does not require you to actually use MS Project.
You are responsible for managing a project's schedule in MS Project. Among other tasks, the schedule contains a gardening task, which is defined as follows:
The tasks duration is days.
The task is defined as an autoscheduled, effort driven, fixed duration task.
The following resources have been allocated to the task:
Resource Name Units Resource Type
gardener Work
Looking at the project options in MS Project, you find that one day equals hours.
How many manhours in total are associated with this gardening activity according to MS Project? If necessary, round to two decimal places.
manhours
It is now decided that additional gardeners should be added to the gardening task.
So you increase the number of gardeners by in the Task Information dialog for the for the gardening task.
What is the new task duration in MS Project? If necessary, round to two decimal places.
days
What is the new total of manhours associated with this task in MS Project? If necessary, round to one decimal place.
manhours
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock