Question: Note : urgent and full answer required I'll give you like and comment please it's really really urgent Question # 1 A project is specified

Note : urgent and full answer required I'll giveNote : urgent and full answer required I'll give you like and comment please it's really really urgent

Question # 1 A project is specified by the following activities (6): Activity Immediate Predecessor(s) Duration (days) 15 TO OWO A A, B A B C, D, E E, F 8 15 6 9 20 10 a) Construct an activity on node or arrow network to represent the above project. b) Calculate the earliest start, latest start, earliest finish and latest finish times for each activity c) Identify and calculate the critical path.(forward pass only)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!