Question: Note: Use the Workday project scenario from Assignment 1 . Additional Project Scenario: Your project is going to slip unless you take action. You are

Note: Use the Workday project scenario from Assignment 1.
Additional Project Scenario:
Your project is going to slip unless you take action. You are the Project Manager and just found out:
Donna and David have not completed the test scenarios- and she's going on vacation for 2 weeks. This task is already 4 weeks behind schedule.
Note the impact this will have on all of the activities that occur after testing.
Note the potential solutions to get back on track.
Note the costs / timelines associated.
Ensure you have a few options (option A and B- at a minimum)
Pick an option and note why it was selected.
Discuss who will give approval of this modification and how you'd present the information.
The project team requests a formal status report - if they had this they may have been able to see this delay in a more timely fashion. Review Table 13.2 report for 3 periods. Note the EV, AC, PV, CV, and SV (you can make up numbers but I do want to see calculations on how you arrived at these values). the percentages means to the overall project.
Note: Use the Workday project scenario from

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!