Question: Note: You do not need to solve the linear program, I just need the notation for the decision variables, objective, and constraints with an explanation.

Note: You do not need to solve the linear program, I just need the notation for the decision variables, objective, and constraints with an explanation.
6. A project consists of seven activities. The precedence relationships are given in the following table. 14. Solve Problem 6 by linear programming. Using information given in problem 6 , create a linear program to determine the critical pathStep by Step Solution