Question: NPV 3. Giambona Industries is considering Project AA whose future expected cash flows are shown below. However, the up-front cost of the project (X) is
NPV
3. Giambona Industries is considering Project AA whose future expected cash flows are shown below. However, the up-front cost of the project (X) is not given. You are told that the project has a WACC of 10% and that the projects NPV is zero. Based on this information, what is the up-front cost of the project, i.e., what is X?
WACC = 10%
Year: 0 1 2 3 4
CFS: X $624 $440 $150 $ 18
a. -$ 488.63
b. -$ 677.70
c. -$ 866.81
d. -$1,055.90
e. -$1,232.00
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
