Question: NT 4 6 0 0 . 5 3 5 7 4 . 2 0 2 5 1 [ Based on Certified Associate in Project Management
NTBased on Certified Associate in Project Management CAPM Based on PMBOK
You are managing a project to open a new call center in a different city to supplement your existing call center staff. You have identified a risk that you might not find the staff by the time the call center opens. You decide to work with a headhunter who has guaranteed that they will find all the staff needed with the appropriate skill sets by the time the center opens; they have agreed to pay a penalty if they fail at this. What risk response strategy does this indicate?
A Transfer
B Exploit
C Share
D Mitigate