Question: O = Optimistic time/ Best Case Scenario M = Most Likely P = Pessimistic Time / Worst Case Scenario Calculate the Float/Slack on the non-critical
O = Optimistic time/ Best Case Scenario
M = Most Likely
P = Pessimistic Time / Worst Case Scenario
- Calculate the Float/Slack on the non-critical activities and state whether it is Total Float or Free Float.
- What is the standard deviation for each activity?
TASK TIME (Days) PRECEDING
TASK O M P TASK
A 3 5 7 -----
B 8 9 10 -----
C 1 2 3 A
D 5 10 15 B
E 5 7 9 B
F 4 5 6 C, D
G 3 4 5 D, E
H 5 7 9 F, G