John Dow has constructed the incomplete time-phased MPS record shown. Suppose John Dow prepares the product in batches of Q=70 units. It takes one week to make a batch of 70 units. Safety stock is 15 units. On hand =70. Complete the MPS schedule. (2 pts) The XYZ company has constructed the following incomplete record. On hand =130 and the MPS production lot size is Q=100. Assume no safety stock and no lead time. Complete the record. (3 pts)