Question: o Question 2 At zero direct labor hours in a flexible budget graph, the total budgeted cost line intersects the vertical axis at $30000. At
o Question 2 At zero direct labor hours in a flexible budget graph, the total budgeted cost line intersects the vertical axis at $30000. At 10000 direct labor hours, a horizontal line drawn from the total budgeted cost line intersects the vertical axis at $70000. Fixed and variable costs may be expressed as: $30000 fixed plus $4 per direct labor hour variable. $40000 fixed plus $4 per direct labor hour variable. $30000 fixed plus $7 per direct labor hour variable. $40000 fixed plus $3 per direct labor hour variable. O