Question: O Stock E D Question 7 3 pts )Project A has a beta of 0.69 and an IRR of 9.27 percent. Project B has a

 O Stock E D Question 7 3 pts )Project A has

O Stock E D Question 7 3 pts )Project A has a beta of 0.69 and an IRR of 9.27 percent. Project B has a 1.13 beta and an IRR of 11.58 percent. Which one of these projects will you accept and which will you reject if the risk-free rate of return is 3.6 percent and rate of return is 10.8 percent? (round answer to 4 digits. Think about SM O Accept Project A and Project B Reject Project A and Project B. O Accept Project A and reject Project B O Reject Project A and accept Project B O Don't know. 1 pts D Question 8