Question: ob 910 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 2,461 Direct labor-hours 74 labor-hours Direct
ob 910 was recently completed. The following data have been recorded on its job cost sheet:
| Direct materials | $ 2,461 | |
|---|---|---|
| Direct labor-hours | 74 | labor-hours |
| Direct labor wage rate | $ 18 | per labor-hour |
| Machine-hours | 137 | machine-hours |
The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $19 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 910 would be: