Question: ob A 3 B was ordered by a customer on September 2 5 . During the month of September, Jaycee Corporation used $ 2 ,
ob AB was ordered by a customer on September During the month of September, Jaycee Corporation used $ of direct materials and used $ of direct labor. The job was not finished in September. An additional $ of direct materials and $ of direct labor were needed to finish the job in October. The company applies overhead at the end of each month at a rate of of the direct labor cost incurred. What is the total cost of the job when it is completed inOctober?