Question: ob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete. Due to
ob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete. Due to the uncertainty involved he will be making a low, an average and a high estimate. Rob is using which estimating approach?
Question Select one:
A
Parametric procedures applied to specific tasks
B
Template method
C
Apportion method
D
Range estimating
E
Learning curve