Question: Och, Inc., is considering a project that will result in initial aftertax cash savings of $1.77 million at the end of the first year, and

Och, Inc., is considering a project that will result in initial aftertax cash savings of $1.77 million at the end of the first year, and these savings will grow at a rate of 1 percent per year indefinitely. The firm has a target debtequity ratio of .75, a cost of equity of 11.7 percent, and an aftertax cost of debt of 4.5 percent. The cost-saving proposal is somewhat riskier than the usual projects the firm undertakes; management uses the subjective approach and applies an adjustment factor of +2 per cent to the cost of capital for such risky projects.

What is the maximum initial cost of company would be willing to pay for the project? (Do not round intermediate calculations. Enter your answer in dollars, not millions of dollars, i.e. 1,234,567.)

Answer is NOT $18,247,423, 18.60 million, 22,530,120, and not 26,878,356.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!