Question: od More Info 2 E Activity A B - Duration (days) 6.5 1 2.5 7 6 4.5 2 Predecessors None None A AB CD D

od More Info 2 E Activity A B - Duration (days)
od More Info 2 E Activity A B - Duration (days)
od More Info 2 E Activity A B - Duration (days) 6.5 1 2.5 7 6 4.5 2 Predecessors None None A AB CD D E, F B Print Dono D b. Identify all the paths through the network and their lengths. Fill in the table below (enter your responses rounded to one decimal place). Length (days) Path A.C. AL Anar