Question: Of every 100 units processed, each work station performs as follows: stn#1 = 90 processed correctly the first time and 10 defectives repaired and successfully
Of every 100 units processed, each work station performs as follows: stn#1 = 90 processed correctly the first time and 10 defectives repaired and successfully re-introduced in the process stn#2 = All units processed correctly the first time stn#3 = 95 processed correctly the first time and 5 defectives repaired and successfully re-introduced in the process stn#4 = All units processed correctly the first time What is the Yield and the First Pass Yield of the process? (Remember Process yields are a multiplicative function of workstep yields)
A. Yield = 0.98 (98%) FPY = 0.86
B. Yield = 1.00 (100%) FPY = 0.86
C. Yield = 0.86 FPY = 1.00 (100%)
D. Yield = 1.00 (100%) FPY = 0.96