Question: Office Automation developed a proposal for introducing a new computerized office system that will improve word processing and interoffice communications for a particular company. Contained
Office Automation developed a proposal for introducing a new computerized office system that will
improve word processing and interoffice communications for a particular company. Contained in the
proposal is a list of activities that must be accomplished to complete the new office system project. Use
the following relevant information about the activities:
The normal duration of activity B is uncertain as well as the crash time of activity F The estimated
weeks are as follows respectively:
Most optimistic time B F
Most likely time B F
Most pessimistic time B F
Activity Description Immediate
Predecessor
Time weeks Cost Cost slope
Normal Crash Normal Crash
A Plan needs
B Order equipment A
C Install equipment B
D Set up training lab A
E Conduct training
course
D
F Test system C E
REQUIRED:
Draw a network diagram based on the normal times given, illustrating the critical path routes
and determine the normal cost and duration to complete the project.
Determine ES EF LS LF and slack for each activity
Calculate the crash cost for activity D and crash time for activity F
Assume that the company wants to complete the project in six months or weeks. What
crashing decision do you recommend to meet the desired completion time at the least possible
cost Work through the network and attempt to make the crashing decision by inspection
indicate clearly the additional cost of crashing.
Determine ES EF LS LF and slack for each activity for the crashed project and what is the added
project cost required to meet the six month completion time
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock