Question: Office Min is considering several risk-free projects: Project Initial cash flow Cash flow in 1 year A -9,300 11,160 B -4,000 4,200 C -6,600 7,590
Office Min is considering several risk-free projects:
| Project | Initial cash flow | Cash flow in 1 year |
| A | -9,300 | 11,160 |
| B | -4,000 | 4,200 |
| C | -6,600 | 7,590 |
The risk-free interest rate is 8%.
What is the NPV of project C?