Question: Often, two or more concurrent tasks depend on a single prior task, which is called a _ _ _ _ _ . a . beneficiary

Often, two or more concurrent tasks depend on a single prior task, which is called a _____.
a. beneficiary task
b. wireframe task
c. predecessor task
d. discrete task