Question: Old MathJax webview Please give the answer according to the requirements of the above Questions. thank you . 22. Using the information provided in the
Old MathJax webview

Please give the answer according to the requirements of the above Questions. thank you
.
22. Using the information provided in the following table, create a network diagram using the precedence diagram method and determine the duration of the project and the critical path. Activity Predecessor Duration Start None 5 B A 2 A 3 (Continued) 33 Activity Predecessor Duration Duration D B 7 E 4 F D 1 G E,F 2 End G Project Duration Critical Path The vaua wau pana in uscu W UCIC the latest start and latest finish of each activity. In diagrams where all relationships are finish to start, the difference between the latest finish and the earliest finish will determine the float or slack for the activity. There is generally no float or slack on the critical path. The backward pass is performed on the network diagram from the end milestone and proceeding back through the network to the starting point. At points of convergence the smaller number is used to determine the latest finish of a preceding task. 23. Referring to the diagram developed in question 6, perform a backward pass to determine the late start and late finish of each activity. a. Identify the activities that have float or slack. Activity Predecessor Duration Float/Slack Start None 5 B A 2 A 3 D B 7 E 4 F D 1 G E.F 2 End G b. What is the early start of Activity C? c. What is the late start of Activity EStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
