Question: old Star LAN Project: You work for an IT consulting & engineering firm and is assigned to the Gold Star LAN project. It's a small

old Star LAN Project:
You work for an IT consulting & engineering firm and is assigned to the Gold Star LAN project.
It's a small project which involved laying of LAN cables at the Corporate office of the client
firm - Gold Star. The approved completion time of the project is 11 weeks. The high level
project schedule has four work packages A, B, C, D. Baseline Project schedule along with
budgeted cost is given below:
Work
Package
c
Total
Approved WI w2 w3 w4 w5 w6 w7 w8 w9 w10 WII
Cost ($)
4000
8000
4000
3000
19000
Assume that planned work progress and budgeted costs is distributed on prorate basis.
Project has started and 6 weeks have already passed. At the end of 6th week, your team
members have reported the work progress and actual expenditures as follows:
Work Package A: 100% completed, however actual completion time is 5 weeks instead of
4 weeks. Actual cost of completion is $5000.
Work Package B: 40% work completed. Actual expenditure incurred $5000.
Work Package C: 20% work completed. Actual expenditure incurred $3000.
Answer the following.
a) Construct Cost Baseline of the Gold Star LAN Project.
b) Employing Earn Value Management (EVM) technique to monitor and control the
project, evaluate PV, EV, CV, SV of the project as on end of 6th week.
c) Forecast the completion time of the project and project cost at completion.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!