Question: old Star LAN Project: You work for an IT consulting & engineering firm and is assigned to the Gold Star LAN project. It's a small
old Star LAN Project:
You work for an IT consulting & engineering firm and is assigned to the Gold Star LAN project.
It's a small project which involved laying of LAN cables at the Corporate office of the client
firm Gold Star. The approved completion time of the project is weeks. The high level
project schedule has four work packages A B C D Baseline Project schedule along with
budgeted cost is given below:
Work
Package
c
Total
Approved WI w w w w w w w w w WII
Cost $
Assume that planned work progress and budgeted costs is distributed on prorate basis.
Project has started and weeks have already passed. At the end of th week, your team
members have reported the work progress and actual expenditures as follows:
Work Package A: completed, however actual completion time is weeks instead of
weeks. Actual cost of completion is $
Work Package B: work completed. Actual expenditure incurred $
Work Package C: work completed. Actual expenditure incurred $
Answer the following.
a Construct Cost Baseline of the Gold Star LAN Project.
b Employing Earn Value Management EVM technique to monitor and control the
project, evaluate PV EV CV SV of the project as on end of th week.
c Forecast the completion time of the project and project cost at completion.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
