Question: ( OMD ) is developing a next generation infusion pump for hospitals worldwide. The design must be finalized, tested, and approved before production can begin.
OMD is developing a next generation infusion pump for hospitals
worldwide. The design must be finalized, tested, and approved before production can begin. Because of increasing competition, OMD faces two major pressures:
TimetoMarket: Each week of delay beyond the target launch date results in lost hospital contracts and lower revenue for the new device.
Design Quality and Cost: A more thorough engineering process with advanced design techniques generally yields lower variable costs and fewer postlaunch defectsbut also entails higher upfront investment.
You have been asked to recommend how Oriole Medical Devices should proceed with the product design. Your task is to:
Identify the decision alternatives and any subsequent branches in the decision tree
Estimate the financial outcomes revenues costs, and penalties associated with each possible scenario.
Determine the best decision using an expected monetary value EMV criterion.
Decision Alternatives
OMD has three main ways to complete the design:
Internal RapidFire Team IRapid
o Uses only OMDs inhouse engineers on a crash schedule.
o Fixed Cost: $ total includes overtime, crash scheduling, etc.
o Weekly Penalty if Late: $week
o Time to Completion probabilistic:
On Time weeks: chance
week late weeks: chance
weeks late weeks: chance
weeks late weeks: chance
Premium Outsourcing Outsource
o A specialized external design consultancy.
o Fixed Cost: $
o This team is larger and has sophisticated tools, so it rarely runs late.
o Weekly Penalty if Late: $week
o Time to Completion probabilistic:
On Time weeks:
week late weeks:
weeks late weeks:
No chance of being more than weeks late
Hybrid Approach Hybrid
o Split the work: An external contractor handles mechanicalelectronic subsystems; OMDs staff does the software portion.
o Fixed Cost: $ external $ internal $ total.
o Weekly Penalty if Late: $week
o Time to Completion probabilistic:
On Time weeks:
week late weeks:
weeks late weeks:
weeks late weeks:
Potential InformationGathering Decision
Before choosing one of the three design paths, OMD could pay $ for a thorough risk assessment a fast but detailed feasibility study by a consulting firm. This study would update the timetocompletion probabilities for each option with more accurate data:
If the studys results indicate High Feasibility chance then the ontime probabilities for each design option increase by percentage points, and each late scenarios probability decreases proportionally.
If the studys results indicate Low Feasibility chance then the ontime probabilities for each design option decrease by percentage points, and each late scenarios probability increases proportionally.
OMD must decide first whether to pay $ for the study. If it does pay, it can then choose after learning the result which of the three design options to pursue.
Revenue Implications
FullPrice Revenue for an ontime launch is $ million weeks
If launched one week late, total revenue drops to $ million.
If launched two weeks late, total revenue drops to $ million.
If launched three weeks late, total revenue drops to $ million.
Launches later than weeks beyond target bring in only $ million
Your Tasks
Build the Decision Tree
Assign Monetary Outcomes
o Account for each design options fixed cost, possible late penalties, and resulting revenue.
Calculate the EMV
o Compute the expected monetary value for each possible sequence of decisions.
o Identify which option or sequence of options is the best choice.
Managerial Recommendation
o State which approach you would recommend and why.
o Comment briefly on whether OMD should purchase the feasibility study and how that changes the EMV versus skipping the study
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
