Question: ( OMD ) is developing a next generation infusion pump for hospitals worldwide. The design must be finalized, tested, and approved before production can begin.

(OMD) is developing a next generation infusion pump for hospitals
worldwide. The design must be finalized, tested, and approved before production can begin. Because of increasing competition, OMD faces two major pressures:
1. TimetoMarket: Each week of delay beyond the target launch date results in lost hospital contracts and lower revenue for the new device.
2. Design Quality and Cost: A more thorough engineering process (with advanced design techniques) generally yields lower variable costs and fewer postlaunch defectsbut also entails higher upfront investment.
You have been asked to recommend how Oriole Medical Devices should proceed with the product design. Your task is to:
Identify the decision alternatives (and any subsequent branches in the decision tree).
Estimate the financial outcomes (revenues, costs, and penalties) associated with each possible scenario.
Determine the best decision using an expected monetary value (EMV) criterion.
Decision Alternatives
OMD has three main ways to complete the design:
1. Internal RapidFire Team (IRapid)
o Uses only OMDs inhouse engineers on a crash schedule.
o Fixed Cost: $130,000 total (includes overtime, crash scheduling, etc.).
o Weekly Penalty if Late: $25,000/week.
o Time to Completion (probabilistic):
On Time (12 weeks): 40% chance
1 week late (13 weeks): 35% chance
2 weeks late (14 weeks): 15% chance
3 weeks late (15 weeks): 10% chance
2. Premium Outsourcing (Outsource)
o A specialized external design consultancy.
o Fixed Cost: $180,000.
o This team is larger and has sophisticated tools, so it rarely runs late.
o Weekly Penalty if Late: $25,000/week.
o Time to Completion (probabilistic):
On Time (12 weeks): 70%
1 week late (13 weeks): 20%
2 weeks late (14 weeks): 10%
(No chance of being more than 2 weeks late)
3. Hybrid Approach (Hybrid)
o Split the work: An external contractor handles mechanical/electronic subsystems; OMDs staff does the software portion.
o Fixed Cost: $90,000 external + $60,000 internal = $150,000 total.
o Weekly Penalty if Late: $25,000/week.
o Time to Completion (probabilistic):
On Time (12 weeks): 30%
1 week late (13 weeks): 40%
2 weeks late (14 weeks): 20%
3 weeks late (15 weeks): 10%
Potential InformationGathering Decision
Before choosing one of the three design paths, OMD could pay $30,000 for a thorough risk assessment (a fast but detailed feasibility study) by a consulting firm. This study would update the timetocompletion probabilities for each option with more accurate data:
If the studys results indicate High Feasibility(60% chance), then the ontime probabilities for each design option increase by 10 percentage points, and each late scenarios probability decreases proportionally.
If the studys results indicate Low Feasibility(40% chance), then the ontime probabilities for each design option decrease by 10 percentage points, and each late scenarios probability increases proportionally.
OMD must decide first whether to pay $30,000 for the study. If it does pay, it can then choose (after learning the result) which of the three design options to pursue.
Revenue Implications
FullPrice Revenue for an ontime launch is $1.5 million (12 weeks).
If launched one week late, total revenue drops to $1.4 million.
If launched two weeks late, total revenue drops to $1.25 million.
If launched three weeks late, total revenue drops to $1.1 million.
Launches later than 3 weeks beyond target bring in only $1.0 million
Your Tasks
1. Build the Decision Tree
2. Assign Monetary Outcomes
o Account for each design options fixed cost, possible late penalties, and resulting revenue.
3. Calculate the EMV
o Compute the expected monetary value for each possible sequence of decisions.
o Identify which option (or sequence of options) is the best choice.
4. Managerial Recommendation
o State which approach you would recommend and why.
o Comment briefly on whether OMD should purchase the feasibility study and how that changes the EMV versus skipping the study

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!