Question: On a PERT chart, an arrow from Activity D to Activity E indicates that _ _ _ _ _ _ _ . Question

On a PERT chart, an arrow from "Activity D" to "Activity E" indicates that_______.
Question content area bottom
Part 1
A.
this is the critical path for the project
B.
Activity D must be completed before Activity E can start
C.
Activity E will take longer to complete than Activity D
D.
Activity D takes longer to complete than Activity E
E.
both activities can be completed simultaneously