Question: On a PERT chart, an arrow from Activity D to Activity E indicates that _ _ _ _ _ _ _ . Question
On a PERT chart, an arrow from "Activity D to "Activity E indicates that
Question content area bottom
Part
A
this is the critical path for the project
B
Activity D must be completed before Activity E can start
C
Activity E will take longer to complete than Activity D
D
Activity D takes longer to complete than Activity E
E
both activities can be completed simultaneously