Question: On a work package for Create RFP for consulting Services', you want to avoid subjective estimates of completion, for the earned value management. You could
On a work package for "Create RFP for consulting Services', you want to avoid subjective estimates of completion, for the earned value management. You could choose the method
Apportioned
Weighted milestones
Equivalent completed units
Percent complete