Question: on an assembly line, and there are six steps that need to be completed for assembly. The demand for the control panel is 4 ,
on an assembly line, and there are six steps that need to be completed for assembly. The demand for the control panel is units per hour workweek:
tableTasktablePerformance TimesecondsPredecessorsABACADAEB CFD E
a Given the demand, the cycle time for the production of the new control panel seconds round your response to one decimal place
b The theoretical minimum number of workstations round your response up to the next whole number
tableTaskWorkstation #AVBCDEF
Were you able to assign all the tasks to the theoretical minimum number of workstations?
d The total idle time per cycle for the process seconds enter your response as a whole number
e The efficiency of the assembly line with workstations enter your response as a percentage rounded to one decimal place
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock