Question: On another matter the Project Manager has received a notification of a compensation event from the Contractor. The Project Manager believes the matter is a

On another matter the Project Manager has received a notification of a compensation event from the Contractor. The Project Manager believes the matter is a compensation event. Which TWO of the following statements best represent the actions now required by the Project Manager?
Select TWO options
Reply to the Contractor within the period for reply notifying the Contractor that the event is a compensation event.
Reply to the Contractor within one week notifying the Contractor that the event is a compensation event.
Reply to the Contractor within one week notifying the Contractor that the event is a compensation event and separately give an instruction to the Contractor to submit quotations.
Reply to the Contractor within one week notifying the Contractor that the event is a compensation event and include an instruction to the Contractor to submit quotations.
Review the Early Warning Register.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!