Question: On April 1 , 2 0 2 5 , Sunland Inc. entered into a cost plus fixed fee contract to construct an electric generator for

On April 1,2025, Sunland Inc. entered into a cost plus fixed fee contract to construct an electric generator for Novak Corporation. At
the contract date, Sunland estimated that it would take 2 years to complete the project at a cost of $1,930,000. The fixed fee
stipulated in the contract is $459,000. Sunland appropriately accounts for this contract under the percentage-of-completion method.
During 2025, Sunland incurred costs of $829,900 related to the project. The estimated cost at December 31,2025, to complete the
contract is $1,100,100. Novak was billed $566,000 under the contract.
Prepare a schedule to compute the amount of gross profit to be recognized by Sunland under the contract for the year ended
December 31,2025.(If an amount reduces the account balance then enter with negative sign., e.g.-45 or parentheses e.g.(45).)
SUNLAND INC.
Computation of Gross Profit to be
Recognized on Uncompleted Contract
Year Ended December 31,2025
Total Contract Price
Estimated Contract Cost at Completion
Fixed Fee
Total
Total Estimated Cost
Gross Profit
Percentage of Completion
Gross Profit to be Recognized
$
 On April 1,2025, Sunland Inc. entered into a cost plus fixed

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!