Question: On April 1 , 2 0 X 1 , Burchell Construction contracted with The Horton Group to build a parking garage for $ 1 ,
On April X Burchell Construction contracted with The Horton Group to build a parking garage for $ The Horton Group is offering a performance bonus of $ if the garage is completed by June ; the bonus is reduced by $ for each week that completion of the project is late. Based on experience with similar contracts, Burchell estimates the following probabilities regarding completion of the garage:
tableCompletion date,Probability of completionJune