On April 1, 2020, Waleed company entered into a cost-plus fixed-fee contract to construct a power station,
Fantastic news! We've Found the answer you've been seeking!
Question:
On April 1, 2020, Waleed company entered into a cost-plus fixed-fee contract to construct a power station, estimated to complete in 2 years at a cost of $6,000,000. The fixed fee stipulated in the contract is $900,000. During the year Waleed company incurred cost of $1,600,000. The estimated cost at December 31, 2020 to complete the contract is $2,400,000 and billed for $1,200,000.
Prepare a schedule to compute amount of gross profit to be recognized under the percentage of completion method.