Question: On January 1 , 2 0 1 9 , Basker Research signed a contract to have Bob's Builders construct a laboratory building at a cost

On January 1,2019, Basker Research signed a contract to have Bob's Builders construct a laboratory building at a cost of $20,000,000. It was estimated that it would take four years to complete the project. Also on January 1,2020, to finance the construction cost, Tolvin borrowed $20,000,000 payable in five annual installments of $4,000,000 plus interest at the rate of 7%. During 2020, Tolvin made the following construction-related expenditures:
DateAmount3/1$600,0007/1$700,00011/1$900,000
What amount should Tolvin report as capitalized interest at December 31,2020?
$152,000
$1,400,000
$70,000
$84,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!