Question: On January 1 , 2 0 2 2 , Winter Harvest Ltd . started a construction project for $ 4 , 5 0 0 ,

On January 1,2022, Winter Harvest Ltd. started a construction project for $ 4,500,000. Relevant data for 2022 and 2023 are as follows:
20222023
Current year construction costs $ 3,300,000 $ 620,000
Estimated remaining costs to complete 600,000-0-
Current year billings 3,100,0001,400,000
Current year collections 3,000,0001,500,000
Required
1. Calculate the following amounts for each method:
2. Completed Contract Percentage of Completion
2022202320222023
Gross Profit $ ? $ ? $ ? $ ?
Construction in progress year-end balance. $ ? $ ? $ ? $ ?
Costs in excess of billi\table[[,\table[[Completed],[Contract]],\table[[Percentage of],[Completion]]],[,2022,2023,2022,2023],[Gross Profit,$?,$?,$?,$?ngs (Billings in excess of costs) $ ? $ ? $ ? $ ?
 On January 1,2022, Winter Harvest Ltd. started a construction project for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!